Grenfell Tower: was the cladding really banned material?

Posted on

Was London’s Grenfell Tower, scene of a horrific fire that killed dozens of people, covered in “banned” flammable cladding?   The  answer – worryingly – is probably no. And if that is the case, it exposes the shocking flaws in Britain’s regulatory system for high-rise developments.

The Department of Communities in initially answering this question – before any tests were made on the actual material – said this: “Cladding using a composite aluminium panel with a polyethylene core would be non-compliant with current Building Regulations guidance. This material should not be used as cladding on buildings over 18m in height.”

But this is not the case. Such cladding – described officially as “material of low combustibility” (MOLC) is lawful and recommended above 18 metres, as is the more fire-resistant cladding described officially as “non-combustible”. Composite aluminium panels with a polyethylene core may well meet the standard as MOLC. So, as long as the suppliers didn’t do some sort of substitution with inferior stuff, such panels are lawful.

This is what the government Building Regulations Approved document B of 2010 vol 2 actually say:

12.5 The external envelope of a building should not provide a medium for fire spread if it is likely to be a risk to health or safety. The use of combustible materials in the cladding system and extensive cavities may present such a risk in tall buildings.

This gives a hint of the rather vague regulatory framework that applies to materials in buildings – almost a statement of the obvious, leaving suppliers, builders and inspectors simply to do their best to ensure safety. As to cladding for high-rise blocks, the document goes on to say:

Insulation Materials/Products
12.7  In a building with a storey 18m or more above ground level any insulation product, filler material (not including gaskets, sealants and similar) etc. used in the external wall construction should be of limited combustibility (see Appendix A)
.”

So this is where DCLG got it’s 18 metres from. But by no means is this a ban on the sort of material (probably) used on Grenfell Tower. Indeed “limited combustibility” is the standard for this sort of work. The guidelines do not even suggest using the higher standard “non-combustible” material. At B4 (1) (page 91), the document says:

“The external walls of the building shall adequately resist the spread of fire over the walls and from one building to another, having regard to the height, use and position of the building.”

The test used is to apply flames to the surface (not the polyethylene core) of the panels. Here is what a manufacturer of building materials (not those used on Grenfell Tower) has to say by way of explanation of the standard:

“It is important to note that a Surface Spread of Flame Classification does not infer [ie imply] any resistance to combustibility; it is solely a measure of the spread of a flame across the material’s surface.” (Rockwool Ltd, page 4).

Yet that is sufficient to meet the standard. It concludes that for the builder or developer: “The first and by far least restrictive option is to use materials of limited combustibility (MOLC) for all elements of the cladding system that are situated both above and below 18m.”

It is “least restrictive” because in effect it is pre-assessed as being acceptable for this sort of job: it reaches an “EN reaction to fire classification” of A2. Otherwise the developer would have to go through a process of getting clearance for the materials it wants to use from the independent testing body, UKAS (the BS8414 Test which would produce a report showing the BR135 specification has been met – see below.)

So above 18 metres “material of low combustibility” (MOLC) is standard. And, of course, “non-combustible” material could be used too (A1 on the reaction to fire classification). This is the material, that would, according to some news reports, cost only £2 a square metre more than the Reynobond PE aluminium with polyethylene core cladding apparently ordered for Grenfell  Tower.

Suppliers Omnis Exteriors said they were asked for Reynobond PE cladding, which is MOLC. This aluminium composite material (ACM) would have met the standard, designated “Class 0 rating for the surface spread of flame” and the A2 “reaction to fire classification” – accepted as suitable for this use.

Similarly the Celotex RS5000 infill lagging behind the panels, found to be flammable in new tests after the fire, is according to the manufacturers:

“a premium performance PIR insulation board that: Has been tested to BS 8414-2:2005, meets the requirements in BR 135 and the first PIR insulation suitable for rainscreen cladding applications above 18 metres in height; Features Class O fire performance”.

So the Reynobond PE is apparently legal (and presumably the Celotex is too, again on a “low combustibility” basis). But should it be? The material is lab tested for the effect of flames to its aluminium surface, not in situations when it might be broken through to the core or in high temperatures under which the aluminium would burn through.

It certainly should not be legal, according to Phil Barry, managing director of CWB fire safety consultants in Gloucestershire. who told the Guardian:

“We need to do full-scale tests to see how these materials perform in the real world. In a full-scale test, the outside sheet fails, and it exposes the plastic core, which then burns. That’s what causes the problem. We should be saying no combustible materials on buildings above 18m.”

Comment
This whole issue is complicated and no one should think that this post has got to the bottom of those complexities. But it is clear that thinking in terms of a cladding having been “banned” is wrong – and does not begin to address the full issues about Grenfell Tower and all the other such tower blocks with similar issues.

The regulations are composed in “risk to health and safety” terms rather than specifying what is safe and what isn’t. The safety of legal cladding has to be considered in the light of other issues: exits, fire doors, corridors providing (or failing to provide) escape routes, whether fire engines can get there – and the fact that the use people put the buildings to can easily undermine such safety precautions – or the extent to which vulnerable people are housed there. So it is significant that those decanted from Camden flats after the Grenfell Tower fire were asked to move because of suspect gas fittings and faulty fire doors rather than unsafe cladding.

MOLC may be deemed adequate and lawful but only in the context of other issues – creating a mountain of regulatory complexity which explains why tragedies like Grenfell Tower keep happening.

So the regulations (Part B) say:

“0.4 Whilst guidance appropriate to each of these aspects is set out separately in this document, many of the provisions are closely interlinked. For example, there is a close link between the provisions for means of escape (B1) and those for the control of fire growth (B2), fire containment and/or suppression (B3) and facilities for the fire and rescue service (B5) … Interaction between these different requirements should be recognised where variations in the standard of provision are being considered. A higher standard under one of the requirements may be of benefit in respect of one or more of the other requirements. The guidance in the document as a whole should be considered as a package aimed at achieving an acceptable standard of fire safety.”

The Grenfell Tower panels themselves may have been legal ie compliant with the relevant standard – but their use may not have been because of the context in which they were used. The condensation void between the lagging and the panels may have increased the intensity of the fire, for example; there is a suggestion that the creation of corner patterns using the panelling may have been problematic (similarly funnelling and intensifying the flames at that point perhaps?). Were window frames of the right standard? Were the cladding panels slotted together without separators that would have inhibited the flames? Are there sprinklers in place (the regulations added this in 2007: “Sprinkler systems should be provided in blocks of flats exceeding 30m in height”). Is there more than one set of stairs for escape? (In Grenfell Tower the answer is no.)

We can be pretty certain that what happened at Grenfell Tower was illegal – simply because of what happened at Grenfell Tower. It’s a circular logic. The regulations are outcomes-based rather than prescriptive – see 12.5 quoted above: the cladding “should not provide a medium for fire spread if it is likely to be a risk to health or safety”. We know something has gone horribly wrong – but it will be very difficult to establish who is to blame.

Twitter: alrich0660

Note: The Hackitt report into Grenfell did not recommend banning combustible cladding in high-rise buildings but the Government has now (September 2018) announced it will do so: BBC news.

• Sir Martin Moore-Bick has now (30 October 2019) released the first part of his report into the fire. Its findings are summarised here on Inside Housing. It is available here.

It suggests “the most likely explanation was that the deformation and collapse of the uPVC window jamb [in a kitchen] enabled the fire to bypass the window and enter the cavity around the column and between the insulation and aluminium composite material (ACM) panels”. The cladding’s polyethylene core served as a “source of fuel” for the fire and created a “waterfall” of burning.

There was “a total failure of compartmentation”, meaning smoke and fire moved from flat to flat. He rejected the notion that materials used in the insulation boards were a significant factor.

The issue of building regulations will be considered in the second part of the report. Moore-Bick did say, though that it would be an “affront to common sense” to suggest that the external building walls complied with the requirements of building regulations, ie that they adequately resist the spread of fire. This confirms the “circular logic” approach to regulations pointed out above. He said:

“In circumstances where Arconic does not, and could not sensibly, dispute the rapidity and extent of the spread of fire over and around the building (and indeed in its closing statement put forward a number of mechanisms by which it says that could have occurred), I can see no rational basis for contending that the external walls of the building met requirement B4(1), whatever the reason for that might have been.”

He also noted the experts’ view of “its [the cladding system’s] complexity, not so much in terms of its structure, as in terms of the interactions between its various components when exposed to fire”. He would look in Phase 2 of his inquiry at how far “regulations governing their [cladding materials’] use were, and are, adequate to identify and control the potential dangers from downward and horizontal as well as vertical flame spread”. He said:

“I accept the evidence of all three experts that, if a fire started near a window, there was a disproportionately high chance of its spreading into the cladding, given the configuration and materials of the windows and of exterior cladding. In the view of Professor [José] Torero it was almost certain, if not inevitable, that a kitchen fire of the magnitude he had postulated would occur in a building of this nature at some point in its lifetime and that such an occurrence was perfectly foreseeable. Dr [Barbara] Lane expressed the view that the construction detailing around the windows, including the materials and their arrangement, increased the risk of a fire within the flat breaking out into the large cavities surrounding the windows.”

Note from the Hackitt report, May 2018, on cladding:
7.10 In relation to the testing of cladding materials, there is currently a choice between using products of limited combustibility or undergoing a full system test. Using products which are non-combustible or of limited combustibility is undoubtedly the lower risk option. In the new regulatory framework set out by this review and, as set out in Chapter 2, the greater focus required on key safety aspects from the outset means that the use of lower risk materials would be likely to receive approval by the JCA as a robust layer of protection. Where the person undertaking the work chooses the full system testing option, not only must they ensure that the full system is tested but they will also need to ensure that the potential risks are mitigated by ensuring that the system is properly installed and maintained throughout its life cycle, which creates an ongoing and more onerous responsibility beyond supply and installation.”

This piece looks at one of the first “who pays what” cladding cases to come to a tribunal: Citiscape cladding case

This piece in The Conversation concludes that the government suggestion that Grenfell cladding was banned was “nearly correct” but not that the material was specifically banned. It relies on the very general wording of the building advice in Approved Document 7 which points to regulation 7 of the Building Regulations, which says:

Materials and workmanship
7. Building work shall be carried out—
(a materials which—
(i) are appropriate for the circumstances in which they are used
(ii) are adequately mixed or prepared, and
(iii) are used or fixed so as adequately to perform the functions for which they (b) in a workmanlike manner.

This regulation, of course, is something of a statement of the obvious and would have been no use in suggesting at the time that the specific MOLC material that was put up at Grenfell was unlawful per se. Again we are left with the circular logic of UK building regulations.

Approved Document 7 – Materials and workmanship (2013 edition) (PDF 2.2 Mb)

Note. BBC’s World at One has now established that the Government has ordered that the new tests on cladding around the country should be interpreted to include the polyethylene core in determining whether they are made of “material of low combustibility”, not just the surface. Large numbers of the panels, perfectly legal until now (having passed under BS476), are failing this more rigorous test. (BBC WATO 26 June 2017 at 19.30 minutes.)

So this raises a significant financial issue: who should pay for removing what was legal cladding and putting up the new material: councils, who have paid millions to clad their buildings already? Tenants – many of whom will be right-to-buy long leaseholders who have also contributed to cladding previously – will they be stung for the upgrade too? Or the Government, which seems clearly to have botched the whole regulatory scheme from the outset?

Also: experts have criticised the new government tests that are failing huge numbers of cladding panels, which seem to involve simply setting fire to the polyethylene core and declaring it as failed because it burns (obviously). See The Guardian. The manufacturers of Reynobond PE have withdrawn the material from worlwide sale citing the inconsistency of regulatory regimes (The Guardian).

Hackitt review
Dame Judith Hackitt’s post-Grenfell review has now (December 2017) confirmed “the current regulatory system is not fit for purpose in relation to high-rise and complex buildings”. She writes: “Despite being advised at the outset that the regulatory system for building was outcomes and performance-based, I have encountered masses of prescription which is complex and in some cases inconsistent.”

She criticises the concept of “limited combustibility” as “leaving too much open to interpretation” and notes: “As the review has progressed, it has become clear that the whole system of regulation, covering what is written down and the way in which it is enacted in practice, is not fit for purpose, leaving room for those who want to take shortcuts to do so.”

Her Independent Review of Building Regulations and Fire Safety is here. 

Materials
Who did what: Rydon was appointed as the contractor for the Grenfell Tower refurbishment after a public procurement exercise run by the Royal Borough of Kensington and Chelsea. It was said to have submitted “the most economically advantageous” tender. The cladding was supplied by the giant American-based company Arconic, installed by Harley Facades and cut to shape by Omnis Exteriors. The refurbishment work which Rydon carried out also involved the installation of new windows. See Inside Housing.
• Here is a video of a British Standard test for BS 8414 fire performance: Fire test. Note that a whole panel is tested for the external spread of flame. The idea is to test whether a fire breaking out of an opening (such as a window) will result in excessive fire spread up the outside of the building with the fire re-entering at a higher level. The new tests seem to take a piece of the cladding 25 cm2 and burn it, including the exposed polyethylene core – which is why they have been criticised by the industry since they imply vast amounts of cladding will have to be removed..

• This piece from Reuters suggests the Reynobond supplied for Grenfell Tower wasn’t lawful for the building but notes:

“Some safety experts say the regulations are not black and white. The UK uses a ‘principles-based’ approach to regulation which puts an onus on companies to operate safely, based on common understanding of risks and the technology available. This differs to the highly specific ‘rules-based’ approach to regulation taken in the United States. Supporters of the principles-based approach say it avoids the emergence of loopholes and means companies have to take account of new information on risks immediately, rather than wait for a new regulation to be drafted.”

• However a useful piece from Building Design here notes:

“A building over 18m tall must use materials with a classification of B-s3 or better. This suggests both types of Reynobond panel would meet the requirements of Part B for the flammability of external cladding.”

It also says, though, that this is contradicted elsewhere in the regulations where it says over 18 metres it must have a higher rating – A2 or better – which it describes as non-combustible (rather than low combustibility).

• This item describes the European classification system.
This article from Probyn Miers gives a lot of detail on similar high rise fires. It notes:

“In the UK since 2006, under the Regulatory Reform (Fire Safety) Order 2005 (“FSO”), building owners, employers and occupiers have been legally obliged to evaluate fire risk in all buildings other than private dwelling houses.  The FSO is applicable to apartment blocks with common entries, staircases and landings.”

• This from University of Kent Countercurrents suggests social housing has become unmanageable.

Government standards: External fire spread
B4. (1) The external walls of the building shall adequately resist the spread of fire over the walls and from one building to another, having regard to the height, use and position of the building.

External walls
B4.i The construction of external walls and the separation between buildings to prevent external fire spread are closely related. The chances of fire spreading across an open space between buildings and the consequences if it does, depend on:
a. the size and intensity of the fire in the building concerned;
b. the distance between the buildings;
c. the fire protection given by their facing sides; and
d. the risk presented to people in the other building(s)

B4.ii: Provisions are made in Section 12 for the fire resistance of external walls and to limit the susceptibility of the external surface of walls to ignition and to fire spread.

B4.iii Provisions are made in Section 13 to limit the extent of openings and other unprotected areas in external walls in order to reduce the risk of fire spread by radiation

BR135 include the following:
■ External and Internal Fire Spread – determined by a 600ºC rise in temperature on the external/internal face of the building (measured at a point approximately one storey above the fire floor) for thirty seconds or more during the initial fifteen minutes of the test.
■ Mechanical Performance – determined by an assessment of building collapse, spalling, delamination, flaming debris or fire pool.

About alrich

Journalist and blogger on legal and financial/economics issues

12 responses »

  1. I know corporate lawyers will agree with you on how vague everything is, but i’m not sure a judge would. There is more clarity than you suggest, although you have to pay close attention to follow the trail.

    My own research on this is that Reynobond PE claims certification to BS476-6/7 fire safety standards, but not to BR135/BS8414. Although the Celotex core claims certification to BR135/BS8414, the Reynobond PE product as a whole does not (at least not on its own website).

    Therefore Reynobond PE does not comply with regs AppDoc B vol2 para 12.5, which clearly state BR135/BS8414. That leaves 2 options for compliance – the existence of desktop review confirming that the BS476-6/7 standard is sufficient to comply with BS8414 (BCA guidance allows for such a review, which makes sense in law), or a ‘holistic’ fire safety-engineered approach (AD B vol 2 intro).

    The holistic approach is surely next-to-impossible on a refurb with no sprinklers and no fire escapes. So the case appears to hinge on whether desktop review exists that Reynobond’s BS476-6/7 testing and certification would get it through the BS8414 tests. If so, then regs appear to have been met. If not, then regs have been broken.

    Reply
    • PS to last msg, My point there deals with the case that the materials are classed as combustible, whereas i note your article makes a case for their classification as of ‘limited.combustibility’

      I think the evidence so far in the public domain, especially current tests being performed, is that the polyethylene core is indeed combustible, but i accept that some allowance might be made in law for the details in the specific testing standards. (Reynobond website claims BS476-6/7 certification, but App Doc B vol 2 appx A requires BS476-11 to get ‘limited combustibility’ status. How do these standards differ? Not clear).

      Perhaps even more pertinent to this combustibiity issue, why would Celotex get BR135/BS8414 certification if it had BS476-11 limited combustibility status? (AppDoc B vol2 only requires BS8414 if the material is classed as combustible in the first place). Celotex marketing literature claims BS8414, but pointedly not BS476-11, suggesting its manufacturers are selling it as a combustible material.

      So I’m assuming the Celotex polyethylene is a combustible material for now, although i do accept that the opposite case might yet be made.

      Reply
      • Thanks for these very informative comments. One hopes a judge will be able to see his/her way through this complexity. It’s shocking that one will have to be put to such a task once more.

  2. Derick Tulloch

    I suggest that you compare the Scottish Building Standards, Technical Handbook, Domestic, Part 2, Fire with the regulations you are looking at. There is a reason that no domestic high rise blocks (defined as over 18m) north of the Border have combustible cladding.

    Reply
  3. This is a useful article…http://www.bbc.co.uk/news/uk-40418266
    To me, it seems to describe relevant bodies trying to make their own law. Of course, this is not actually the case … legally speaking, compliance with such guidance surely amounts only to a defence against negligence or criminal misconduct (for the benefit of corporations and their leaders) in the case of a breach of laws, and not a defence against breach of law in itself. These bodies are not authorised to make law. A judge must surely stick up for this point of view.
    I would hope that this whole system is reigned in now, but it’s so complex and many-tentacled that it’s hard to see this happening.

    Reply
  4. The external cladding panels were in compliance with the regs, being Euro Class B and national Class 0; the insulation boards – which incidentally were less dangerous – were not in compliance, since not of ‘limited combustibility’. The main issue is whether the cladding panels can somehow be brought under AD B2 12.5. All attempts to do so fail in my view: http://theriveroflife.com/2017/07/24/grenfell-tower-why-the-acm-panels-were-in-compliance-with-the-building-regulations/

    Andrew

    Reply
  5. Pingback: The Karen Buck Bill: Government gets developers off the hook | AL's LAW

  6. Pingback: Citiscape cladding case at the Property Tribunal | AL's LAW

  7. @DavidLammy MP has posted a string of tweets showing various government spokespeople saying help must be available for recladding – but being very unspecific about what that help will be:

    Reply
  8. Pingback: Citiscape: Tribunal says leaseholders must pay for cladding | AL's LAW

  9. Pingback: Who pays for Grenfell-style cladding? The government plan | AL's LAW

Leave a comment